AGN Gotthardtunnel Los 252 Amsteg – SWITZERLAND

Client
AGN Strabag AG & Mobil Baustoffe GmbH

Project
The section “Amsteg“ consists of two parallel tunnels each 11.4 km long. The total length of the Gotthard-Basistunnel is 57 km.

Our scope of work:

Batching plant

  • Project development
  • Electrical installation

Conveyor system

  • Project development and electrical installation

Concrete loading

  • Process engineering
  • Project development
  • Electrical installation
  • Control system for fully automated concrete loading to the railway wagons to supply the tunnel boring machine (TBM)

Residual water treatmentg

  • Process engineering
  • Project development
  • Electrical installation
  • Control system

for:

  • Processing of tunneling sludge
  • Processing of cleaning water
  • Processing of returned concrete

At this project the entire cleaning water was returned to the cleaning process.